| First Year - FY1999 | Second Year - FY2000 | Totals | 
|---|
 Office of Education | $274,404,000 | $87,769,000 |  | 
|---|
 Virginia Community College System | $68,885,000 | $1,716,000 |  | 
|  C-18 | Improvements:  Repair and Replace Roofs, Virginia Western | $159,000 | $0 |  | 
|  C-19 | Improvements:  Fauquier Campus, Phase I, Lord Fairfax Community College | $317,000 | $0 |  | 
|  C-20 | Improvements:  Connect Campus to City Water Supply, Locust Grove Campus | $418,000 | $0 |  | 
|  C-21 | Construction:  Community Cultural Center:  Middletown | $12,942,000 | $0 |  | 
|  C-22 | Construction:  Arts and Technology Center: Loudoun | $9,850,000 | $0 |  | 
|  C-23 | Construction:  Natural Science Center:  Virginia Western | $400,000 | $0 |  | 
|  C-24 | Construction:  Medical Education Campus, Northern Virginia Community College | $21,710,000 | $0 |  | 
|  C-25 | Construction:  New Academic Building at Virginia Beach | $22,957,000 | $0 |  | 
|  C-26 | Improvements:  Humanities and Social Science Building, Piedmont, Phase II | $132,000 | $1,716,000 |  | 
 University of Virginia | $53,912,000 | $0 |  | 
|  C-27 | Construction:  Campbell Hall Addition | $2,900,000 | $0 |  | 
|  C-28 | Improvements:  Renovate Gilmer Hall, Phase III | $2,500,000 | $0 |  | 
|  C-29 | Improvements:  Renovate Jordan Hall | $2,000,000 | $0 |  | 
|  C-30 | Construction:  Environmental Science Field Station | $2,000,000 | $0 |  | 
|  C-31 | Improvements:  Renovate and Improve Academic & Research Facilities | $8,000,000 | $0 |  | 
|  C-32 | Improvements:  Renovate and Improve Auxiliary Facilities | $3,000,000 | $0 |  | 
|  C-33 | Improvements:  Renovate Pavilion Balconies | $550,000 | $0 |  | 
|  C-34 | Improvements:  Repair Steam Tunnels | $800,000 | $0 |  | 
|  C-35 | Improvements:  Clark Hall Renovation and Addition | $26,412,000 | $0 |  | 
|  C-36 | New Construction:  East Precinct Chiller Plant | $5,750,000 | $0 |  | 
|  University of Virginia Medical Center |   |  | 
|  C-37 | Language Only |   |  | 
|  C-38 | Improvements:  Renovate Digestive Health Center | $3,600,000 | $0 |  | 
|  C-39 | Construction:  Construct or Acquire Child Care Center | $2,400,000 | $0 |  | 
|  C-40 | Construction:  Construct or Acquire Medical Office Building | $4,500,000 | $0 |  | 
|  C-41 | Improvements:  Renovate Medical Center Facilities | $10,000,000 | $0 |  | 
|  Clinch Valley College | $9,726,000 | $0 |  | 
|  C-42 | Improvements:  Renovate and Construct Addition to Science Building | $9,726,000 | $0 |  | 
 Virginia Polytechnic Institute and State University | $4,209,000 | $23,794,000 |  | 
|  C-43 | Construction:  New Chemistry and Physics Building | $1,400,000 | $23,794,000 |  | 
|  C-44 | Planning:  Alumni Center | $809,000 | $0 |  | 
|  C-45 | Improvements:  Renovate Auxiliary Facilities | $2,000,000 | $0 |  | 
|  Virginia Cooperative Extension and Agriculture Experiment Station | $1,167,000 | $0 |  | 
|  C-46 | Planning:  Agriculture and Forestry Research Laboratory Facility | $1,167,000 | $0 |  | 
 Virginia Commonwealth University | $37,043,000 | $9,338,000 |  | 
|  C-47 | Acquisition:  Property to Support Cary, Franklin, Broad and 8th Streets | $1,500,000 | $0 |  | 
|  C-48 | Improvements:  Technology Access Auxiliary Enterprise Facilities | $3,200,000 | $0 |  | 
|  C-49 | Improvements:  Renovate School of Dentistry Building | $2,700,000 | $0 |  | 
|  C-50 | Improvements:  Renovate Hibbs Building | $3,500,000 | $0 |  | 
|  C-51 | Improvements:  Energy Conservation | $2,000,000 | $0 |  | 
|  C-52 | Construction:  Sciences Building | $21,907,000 | $0 |  | 
|  C-53 | Improvements:  Renovate Sanger Hall | $841,000 | $9,338,000 |  | 
|  C-54 | Improvement:  Renovation of Anderson Gallery | $1,395,000 | $0 |  | 
 Old Dominion University | $800,000 | $11,750,000 |  | 
|  C-55 | Construction:  Renovate and Construct An Addition to Constant Hall | $800,000 | $11,750,000 |  | 
 George Mason University | $27,488,000 | $0 |  | 
|  C-56 | Improvements:  Renovate Student Union Facilities | $5,000,000 | $0 |  | 
|  C-57 | Construction:  West Campus Bridge/Road | $4,000,000 | $0 |  | 
|  C-58 | Construction:  Expand General Parking | $500,000 | $0 |  | 
|  C-59 | Construction:  Academic Building Four, Fairfax Campus | $17,988,000 | $0 |  | 
 The College of William and Mary in Virginia | $295,000 | $0 |  | 
|  C-60 | Improvements:  Upgrade Underground Utilities:  Storm Drainage | $295,000 | $0 |  | 
|  Richard Bland College | $642,000 | $340,000 |  | 
|  C-61 | Improvements:  Replace Outside Lighting | $0 | $340,000 |  | 
|  C-62 | Improvements:  Replace and Repair Boiler and Ventilation Systems | $642,000 | $0 |  | 
|  Virginia Institute of Marine Science | $1,794,000 | $0 |  | 
|  C-63 | Improvements:  Replace Gloucester Point Bulkhead | $862,000 | $0 |  | 
|  C-64 | Improvements:  Upgrade Energy Management and Control System | $737,000 | $0 |  | 
|  C-65 | Acquisition:  Wachapreague Property | $195,000 | $0 |  | 
 James Madison University | $5,659,000 | $0 |  | 
|  C-66 | Construction:  New Alumni House | $1,250,000 | $0 |  | 
|  C-67 | Construction:  New Sports Services Building | $1,409,000 | $0 |  | 
|  C-68 | Construction:  Arbotetum Nature Center | $3,000,000 | $0 |  | 
 Christopher Newport University | $668,000 | $2,278,000 |  | 
|  C-69 | Acquisition:  Land on Shoe Lane | $497,000 | $0 |  | 
|  C-70 | Improvements:  Renovate and Construct An Addition to Ratcliffe Gymnasium | $171,000 | $2,278,000 |  | 
 Longwood College | $2,093,000 | $8,587,000 |  | 
|  C-71 | Equipment:  Purchase Equipment for Hiner Building | $1,575,000 | $0 |  | 
|  C-72 | Improvements:  Renovate East, West, and Main Ruffner Complex | $518,000 | $8,587,000 |  | 
 Norfolk State University | $201,000 | $3,392,000 |  | 
|  C-73 | Improvements:  Renovate Communications Building | $201,000 | $3,392,000 |  | 
 Mary Washington College | $2,594,000 | $0 |  | 
|  C-74 | Improvements:  Renovate Combs Hall | $388,000 | $0 |  | 
|  C-75 | Improvements:  Upgrade Goolrick Hall Hvac | $2,206,000 | $0 |  | 
 Radford University | $11,050,000 | $0 |  | 
|  C-76 | Acquisition:  Property for Site Development | $450,000 | $0 |  | 
|  C-77 | Improvements:  Improve Electrical Distribution System | $800,000 | $0 |  | 
|  C-78 | Construction:  Track and Soccer Field, Phase II | $1,900,000 | $0 |  | 
|  C-79 | Improvements:  Improve Steam Distribution System | $715,000 | $0 |  | 
|  C-80 | Construction:  Renovate and Construct Addition to Student Center | $4,622,000 | $0 |  | 
|  C-81 | Improvements:  Renovate Walker Hall | $2,563,000 | $0 |  | 
 Virginia Military Institute | $10,229,000 | $0 |  | 
|  C-82 | Language Only |   |  | 
|  C-83 | Improvements:  Renovate Scott-Shipp Hall | $10,229,000 | $0 |  | 
 Virginia State University | $6,490,000 | $13,780,000 |  | 
|  C-84 | Improvements:  Renovate Rogers Stadium | $2,840,000 | $0 |  | 
|  C-85 | Improvements:  Repair Dormitories, Phase II | $1,939,000 | $0 |  | 
|  C-86 | Improvements:  Renovate Johnston Memorial Library | $1,317,000 | $8,730,000 |  | 
|  C-87 | Improvements:  Renovate Owens Hall | $394,000 | $5,050,000 |  | 
 The Science Museum of Virginia | $357,000 | $3,167,000 |  | 
|  C-88 | Improvements:  Install Fiber Optic Cable | $40,000 | $460,000 |  | 
|  C-89 | Improvements:  Integrate the Science Museum Campus Area | $250,000 | $1,855,000 |  | 
|  C-90 | Improvements:  Renovate East and West Terrace | $67,000 | $852,000 |  | 
 Virginia Museum of Fine Arts | $1,986,000 | $0 |  | 
|  C-91 | Improvements:  Conduct A Fire Suppression System Planning Study | $200,000 | $0 |  | 
|  C-92 | Improvements:  Upgrade the Security Alarm and Access Control System | $1,786,000 | $0 |  | 
 Jamestown-Yorktown Foundation | $6,533,000 | $9,627,000 |  | 
|  C-93 | Improvements:  Jamestown Settlement, Phase II Supplement | $1,155,000 | $0 |  | 
|  C-94 | Improvements:  Jamestown Settlement Cafe | $3,145,000 | $0 |  | 
|  C-95 | Construction:  Linkage Between Visitor Center and the Jamestown Gallery | $385,000 | $4,128,000 |  | 
|  C-96 | Planning:  Park Entry for Jamestown's 2007 Celebration | $0 | $694,000 |  | 
|  C-97 | Planning:  Renovation and Expansion of the Jamestown Gallery | $1,500,000 | $4,805,000 |  | 
|  C-98 | Planning:  Commemorative Monument for 2007 | $125,000 | $0 |  | 
|  C-99 | Planning:  Plan A Plaza for the Commemorative Monument for 2007 | $223,000 | $0 |  | 
 Frontier Culture Museum of Virginia | $83,000 | $0 |  | 
|  C-100 | Construction:  Replace Maintenance Facility | $50,000 | $0 |  | 
|  C-101 | Improvements:  Create Emergency Accessway | $33,000 | $0 |  |