Page 494, line 48, after "5.a.", strike "If", and insert:

"For those projects with a total cost exceeding $12,000,000 for which ".

Page 495, line 1, strike "August" and insert "July".

Page 495, line 1, after "1," strike the remainder of line 1.

Page 495, strike lines 2 through 5.

Page 495, line 6, strike "the detailed list of the Board-approved costs; and any other".

Page 495, line 6, after "any other", insert " all documents and".

Page 495, line 7, after "cost review", insert: "of the project at the completion of preliminary design".

Page 495, line 9, strike "Department of", and insert "Board".

Page 495, line 10, strike "Corrections".



Explanation

(This amendment modifies the process by which local and regional jail renovation, expansion, or construction projects undergo review by the Department of General Services (DGS) in order to qualify for state reimbursement of up to 25.0 percent of project costs in accordance with § 53.1- 80 and § 53.1-81, Code of Virginia, to exempt projects with a total cost of $12.0 million or less from being subject to DGS cost review. DGS review of jail projects was added to the existing Board of Local and Regional Jails review in 2022.)