Authority: Title 10.1, Chapter 11.1; and Title 62.1, Chapters 2, 3.1, 3.2, 3.6, 5, 6, 20, 22, 24, and 25, Code of Virginia.
A. Out of this appropriation, $51,500 the first year and $51,500 the second year from the general fund is designated for annual membership dues for the Ohio River Valley Water Sanitation Commission.
B.1. The permit fee regulations adopted by the State Water Control Board pursuant to paragraphs B.1. and B.2. of § 62.1-44.15:6, Code of Virginia, shall be set at an amount representing not more than 50 percent of the direct costs for the administration, compliance and enforcement of Virginia Pollutant Discharge Elimination System permits and Virginia Pollution Abatement permits.
2. The regulations adopted by the State Water Control Board to initially implement the provisions of this Item shall be exempt from Article 2 (§ 2.2-4006, et seq.) of Chapter 40 of Title 2.2, Code of Virginia, and shall become effective no later than July 1, 2010. Thereafter, any amendments to the fee schedule described by these acts shall not be exempted from Article 2 (§ 2.2-4006, et seq.) of Chapter 40 of Title 2.2, Code of Virginia.
C. Out of the appropriation for this Item, $151,500 the first year and $151,500$205,100 the second year from the general fund is designated for the annual membership dues for the Interstate Commission on the Potomac River Basin.
D.1. Notwithstanding § 62.1-44.15:56, Code of Virginia, public institutions of higher education, including community colleges, colleges, and universities, shall be subject to project review and compliance for state erosion and sediment control requirements by the local program authority of the locality within which the land disturbing activity is located, unless such institution submits annual specifications to the Department of Environmental Quality, in accordance with § 62.1-44.15:56 A (i), Code of Virginia.
2. The State Water Control Board is authorized to amend the Erosion and Sediment Control Regulations (9 VAC 25-840 et seq.) to conform such regulations with this project review requirement and to clarify the process. These amendments shall be exempt from Article 2 (§2.2-4006 et seq.) of the Administrative Process Act.
E. Beginning October 1, 2015, there shall be a $3.75 fee imposed on each dry ton of exceptional quality biosolids cake sewage sludge that is land applied pursuant to § 62.1-44.19:3P, Code of Virginia, until such fee is altered, amended or rescinded by the State Water Control Board.
F. The Department shall work in conjunction with the Virginia Economic Development Partnership to facilitate the development of long-term offsetting methods within the Virginia Nutrient Credit Exchange as set out in Item 113 of this act.
G. Notwithstanding any other provision of law, any Virginia Stormwater Management Program authority is authorized to charge a voluntary fee of $30,000 for review of sites or areas within common plans of development or sale with land-disturbance acreage equal to or greater than 100 acres for an expedited stormwater management program plan review. Any individual or firm electing to pay the voluntary fee shall be guaranteed the total government review time shall not exceed 45 days excluding any applicant's time in responding to questions. Any amounts paid to DEQ above the $9,600 fee shall be used by DEQ to increase the staffing level of the reviewers of these applications.
H. Out of the amounts in this Item, $2,736,330 the first year and $2,736,330 the second year from the general fund is included for the purchase of laboratory and field equipment.
I. Out of the amounts appropriated for this Item, $231,000 the first year and $231,000 the second year is provided for regional water resource planning activities.
J.1. Out of the amounts appropriated for this Item, $1,100,000 the first year and $1,100,000 the second year from the general fund is to be deposited in the Virginia Stormwater Management Fund.
2. Notwithstanding § 62.1-44.15:28, as it is currently effective and as it shall become effective, Code of Virginia, the permit fee regulations adopted by the State Water Control Board pursuant to § 62.1-44.15:28, as it is currently effective and as it shall become effective, Code of Virginia, for the Virginia Pollutant Discharge Elimination System Permit for Discharges of Stormwater from Construction Activities and municipal separate storm sewer system permits shall be set at an amount representing no less than 60 percent, not to exceed 62 percent, of the direct costs for the administration, compliance and enforcement of Virginia Pollutant Discharge Elimination System Permit for Discharges of Stormwater from Construction Activities and municipal separate storm sewer system permits. To the extent practicable, the Board shall solicit input from affected stakeholders when establishing the new fee structure.
3. Notwithstanding § 62.1-44.19:20, Code of Virginia, the application fee schedule adopted by the State Water Control Board pursuant to § 62.1-44.19:20, Code of Virginia, shall be set at an amount representing no less than 60 percent, not to exceed 62 percent, of the direct costs for the administration, compliance and enforcement of the nutrient credit certification program. To the extent practicable, the Board shall solicit input from affected stakeholders when establishing the new fee structure.
K. The Director of the Department of Environmental Quality shall convene a working group for the purpose of developing an annual or project-based fee schedule for the review of erosion and sediment control plans related to solar energy project applications. The working group shall include representatives of (i) private sector companies that own or operate solar energy facilities, (ii) local governments that permit solar facilities, and (iii) other stakeholders determined by the Department to be necessary to the development of the fee schedule.
L. Out of the amounts in this item, $750,000 the first year and $750,000 the second year to establish a mitigation trading platform and wetland in-lieu fee mitigation program consistent with the provisions of § 62.1-44.15:23.1, Code of Virginia.
M. Out of the amounts in this item, $150,000 the first year from the general fund is provided for the department, in collaboration with Virginia Polytechnic and State University and the Smith Mountain Lake Association, to conduct a study of the harmful algal blooms occurring at Smith Mountain Lake. The research shall include evaluation of conditions that have led to the appearance of harmful algal blooms and include recommendations for prevention of further occurrences.
N. Out of the amounts in this item, $500,000 the first year from the general fund is provided to support United States Geological Survey monitoring of harmful algal blooms in the Shenandoah River. Any funds remaining at the end of the fiscal year shall carryforward for the same purpose.
O. Out of the amounts in this item, $250,000 the first year from the general fund is provided for the department, in coordination with the Division of Consolidated Laboratory Services, to provide testing of inland waterways in the Commonwealth for the presence of harmful algal blooms, which may include enumeration of cyanobacteria and associated toxicity analyses. Any funds in this paragraph remaining at the end of the fiscal year shall be carried forward and reappropriated for the same purpose.
P. Out of the amounts in this item, $2,300,000 the first year from the general fund is provided for groundwater research in the Eastern Groundwater Management Area. The appropriation shall be distributed as follows: $2,000,000 for the department to install five additional multi-well research stations to gather additional data to study the upper portions of the Eastern Groundwater Management Area; and $300,000 for the department to conduct a study, in coordination with Virginia Polytechnic Institute and State University, to determine technically feasible locations within the Eastern Groundwater Management Area to recommend water treatment upgrades for Virginia municipal water systems modeled on the Hampton Roads Sanitation District SWIFT project and the cost of such upgrades. The analysis shall be provided to the Chairs of the State Water Commission, House Committee on Agriculture, Chesapeake, and Natural Resources, and Senate Committee on Agriculture, Conservation, and Natural Resources by July 1, 2026. Any funding remaining on June 30 shall be carried forward and reappropriated into the next fiscal year for the purposes described in this paragraph.