| Member Request |  |  | 
| 363#1h | Breaks Interstate Park Dam | $112,500 | $0 | 
| 363#2h | Increase VLCF Funding | $0 | $11,500,000 | 
| 363#3h | Daniel Boone Wilderness Trail Interpretive Center | $209,532 | $159,252 | 
| 363#4h | State Parks Staffing and Operations Costs | $4,981,883 | $4,981,883 | 
| 363#5h | Amend DCR Land Acquisition Restrictions (Language Only) | 
| 363#6h | Land Acquisition New River State Park | $120,000 | $0 | 
| 363#7h | Seven Bends Park Operations | $167,548 | $198,752 | 
| 363#8h | Phase 2 and 3 of Widewater State Park | $965,310 | $590,944 | 
| 363#9h | State Parks Operational Needs | $2,637,896 | $2,637,896 | 
| Committee Approved |  |  | 
| 363#1h | Eliminate New Initiative | -$250,000 | -$250,000 | 
| 363#2h | Land Preservation Funding | -$4,500,000 | $0 | 
| 363#3h | WiFi in State Parks | -$526,888 | -$9,460 | 
| 363#4h | Land Acquisition New River State Park | $120,000 | $0 | 
| 363#5h | Breaks Interstate Park Dam | $112,500 | $0 | 
| Floor Approved |  |  | 
| 363#1h | Eliminate New Initiative | -$250,000 | -$250,000 | 
| 363#2h | Land Preservation Funding | -$4,500,000 | $0 | 
| 363#3h | WiFi in State Parks | -$526,888 | -$9,460 | 
| 363#4h | Land Acquisition New River State Park | $120,000 | $0 | 
| 363#5h | Breaks Interstate Park Dam | $112,500 | $0 |