Item C-157 (Not set out) | First Year - FY2001 | Second Year - FY2002 |
---|
|
|
Improvements: Field Unit Electrical Systems Upgrades (15200) | $200,000 | $800,000 |
Fund Sources: | | |
General | FY2001 $200,000 | FY2002 $800,000 $0 |
Bond Proceeds | FY2001 $0 | FY2002 $800,000 |
A. This appropriation includes bond proceeds for the upgrade of the electrical systems at the following locations:
Haynesville Correctional Unit
Baskerville Correctional Unit
Fairfax Correctional Unit
Appalachian Detention Center
B. This appropriation supplements funding previously provided for this project.