Chief Patron: Jordan
Jarratt Water Distribution System

Item 282 #4s

Item 282 #4s

First Year - FY2027 Second Year - FY2028
Health and Human Resources
Department of Health FY2027 $7,500,371 FY2028 $0 GF

Language
Page 323, line 52, strike "$33,179,983" and insert "$40,680,354".

Page 329, after line 8, insert:

"CC. Out of this appropriation, $7,500,371 the first year from the general fund shall be provided to Greensville County to replace failing asbestos water mains and trunk lines for the Jarratt Water Distribution System."



Explanation

(This amendment provides $7.5 million GF the first year to Greensville County to replace failing asbestos water mains and trunk lines in the Town of Jarratt, Virginia. The Greensville County Water & Sewer Authority (GCWSA) provides potable water to both the Town of Jarratt and the broader Greensville County community. The Jarratt water distribution system serves as a critical hub for the County’s water infrastructure, transporting treated water from the GCWSA water treatment plant northwest of Jarratt to the remainder of the County’s water distribution network. Much of the system was installed in the 1930s using asbestos cement (AC) pipes, which have a useful life of 40 to 50 years. Although some replacements have been made, approximately 95.0 percent of the system remains original. The deteriorating condition of the Jarratt system poses serious risks to public health and safety.)