Chief Patron: Lewis
Cape Charles Harbor Breakwaters
Item 388 #1s
Item 388 #1s | First Year - FY2021 | Second Year - FY2022 | |
Natural Resources |
Marine Resources Commission | FY2021 $1,200,000 | FY2022 $1,200,000 | GF |
Language
Page 388, line 6, strike "$2,989,201" and insert "$4,189,201".
Page 388, line 6, strike "$2,799,101" and insert "$3,999,101".
Page 388, following line 14, insert:
"A. Out of this appropriation, $1,200,000 the first year and $1,200,000 the second year from the general fund is designated to the Town of Cape Charles for construction of two breakwaters and jetty construction to assist with erosion and wave mitigation."
Explanation
(This amendment provides $1.2 million GF in each year to the town of Cape Charles for construction of two breakwaters, one offshore and one inshore, to mitigate the damage from northwest and southwest waves. The appropriation would also go to jetty construction and assist with erosion and wave mitigation.)