Chief Patron: Sickles
Requires Bridge Upgrades as part of Atlantic Gateway Project (language only)

Item 449 #1h

Item 449 #1h

Transportation
Department of Rail and Public Transportation

Language

Page 437, after line 47, insert:

"F. In undertaking the new rail features of the Atlantic Gateway project, the department shall ensure that the existing bridge infrastructure is updated to the Virginia Department of Transportation's standard condition and clearance criteria and that, at a minimum, two-way traffic is accommodated under any bridge on the combined new system crossing a roadway."



Explanation

(This amendment requires that a part of the Atlantic Gateway Project the DRPT ensure that existing bridge infrastructure is updated to VDOT's standard condition and clearance criteria and ensure such structures accommodate two-way traffic.)