Page 472, after line 27, insert:

“z. While the competitive sealed bid process is the preferred method of construction procurement for public bodies, institutions of higher education and state agencies considering the use of Design Build or Construction Management procurement methods for capital projects shall proceed as follows:

1. Institutions of higher education governed under Chapters 933 and 943 of the 2006 Acts of Assembly, Chapters 594, 616, 824 and 829 of the 2008 Acts of Assembly, Chapters 675 and 685 of the 2009 Acts of Assembly, operating under a memorandum of understanding pursuant to §  23-38.90, and those operating under a pilot program under § 4-9.02 shall:

a) Develop a process for determining the selected procurement method which, at a minimum, must consider cost, schedule, complexity, and building use;

b) Submit the process for determining the procurement method to the Department of General Services for review and recommendations;

c) Submit for approval, the the process for determining the procurement method with the Department of General Services recommendations, to the Board of Visitors.

2.  All other institutions of higher education and state agencies shall submit procurement method requests to the Director, Department of General Services for review and approval.

3. Processes for considering Construction Management procurement method shall include, among other processes as determined by the owning institution of higher education or state agency,the following requirements:

a) Cost and project timeline are critical components of the selection process;

b) Construction Management contract will be initiated no later than the Schematic Phase of design unless prohibited by authorization of funding restrictions; and,

c) A written justification that sealed bidding is not practicable and/or fiscally advantageous and such written justification shall be stated in the Request for Qualifications used to procure the Construction Management services.

4. All state entities, including institutions of higher education governed under Chapters 933 and 943 of the 2006 Acts of Assembly, Chapters 594, 616, 824 and 829 of the 2008 Acts of Assembly, Chapters 675 and 685 of the 2009 Acts of Assembly, operating under a memorandum of understanding pursuant to § 23-38.90, and those operating under a pilot program under § 4-9.02 shall report annually, on November 1st of each year,   to the Director, Department of General Services on completed capital projects, beginning with those authorized for construction under Chapter 665 of the 2015 Virginia Acts of Assembly, to include at a minimum procurement method, project budget, actual project costs, expected timeline, actual completion time and any post-project issues. The Department of General Services shall consolidate received report data and submit the consolidated data to the Governor and Chairmen of the House Appropriations and Senate Finance Committees no later than December 1st of each year.  

5. The Auditor of Public Accounts shall, as part of its annual audit plan, determine that institutions of higher education governed under Chapters 933 and 943 of the 2006 Acts of Assembly, Chapters 594, 616, 824 and 829 of the 2008 Acts of Assembly, Chapters 675 and 685 of the 2009 Acts of Assembly, operating under a memorandum of understanding pursuant to § 23-38.90 and those operating under a pilot program under §4-9.02 complied with their internal review process in the selection of procurement method.

6. All state entities, including institutions of higher education governed under Chapters 933 and 943 of the 2006 Acts of Assembly, Chapters 594, 616, 824 and 829 of the 2008 Acts of Assembly, Chapters 675 and 685 of the 2009 Acts of Assembly, operating under a memorandum of understanding pursuant to § 23-38.90 and those operating under a pilot program under § 4-9.02 shall post approved capital projects, beginning with those authorized for construction under Chapter 665 of the 2015 Virginia Acts of Assembly, and approved procurement methods and advertise for project delivery services no less than 30 days publicly on the Commonwealth's statewide electronic procurement system and program, eVA."



Explanation

(This amendment provides for improvements to the capital procurement process and selection of procurement methods for capital projects.)