Item C-133 (Not set out) | First Year - FY2001 | Second Year - FY2002 |
---|
|
|
New Construction: Jamestown Fort (16475) | $617,000 | $0 $2,056,000 |
Fund Sources: | | |
General | FY2001 $617,000 | FY2002 $0 |
Special | FY2001 $0 | FY2002 $600,000 |
Bond Proceeds | FY2001 $0 | FY2002 $1,456,000 |
Funds provided for this Item are for planning.
Out of the amount appropriated to this project in the first year, $564,000 was withheld from expenditure pursuant to Executive Order 74(01) and reverted to the fund balance of the general fund on June 30, 2001.