A.1. This Item authorizes the capital projects listed below to be financed pursuant to Article X, Section 9 (d), Constitution of Virginia.
2. The appropriations for said capital projects are contained in the appropriation Items listed below and are subject to the conditions in § 2-0 F of this act.
3. The total amount listed in this Item includes $125,532,000 $196,932,000 in bond proceeds and $30,843,000 $72,092,000 in higher education operating funds.
AGENCY NAME/PROJECT TITLE | ITEM # | CODE | 9(D) BONDS | HIGHER EDUCATION OPERATING | TOTAL |
| | | | | |
University of Virginia | | | | | |
Aquatic and fitness center | C-54 | 16383 | $5,000,000 | 0 | $5,000,000 |
| | | $6,000,000 | $2,000,000 | $8,000,000 |
Parking Structure | C-60.20 | 16645 | $18,500,000 | $0 | $18,500,000 |
| | | | | |
University of Virginia Medical Center | | | | | |
Kluge Children’s Rehabilitation Center | C-62 | 16245 | $10,000,000 | $27,173,000 | $37,173,000 |
College of William and Mary | | | | | |
Parking deck | C-23 | 16410 | 7,343,000 | 0 | 7,343,000 |
| | | | | |
Longwood College | | | | | |
Fitness center | C-34 | 16420 | 6,000,000 | 6,073,000 | 12,073,000 |
Parking garage | C-37.20 | 16700 | $4,500,000 | $0 | $4,500,000 |
| | | | | |
Virginia Commonwealth University | | | | | |
Bowe Street parking deck, arts laboratory and athletic facility | C-82 | 16406 | 9,600,000 | 0 | 9,600,000 |
| | | 9,900,000 | | 9,900,000 |
Addition to student centers | C-78 | 16401 | 10,000,000 | 0 | 10,000,000 |
Addition to School of Engineering, Phase II | C-80 | 16403 | $26,300,000 | $0 | $26,300,000 |
| | | | | |
Virginia Tech | | | | | |
Career services facility | C-108 | 16477 | 4,608,000 | 0 | 4,608,000 |
Alumni/CEC/hotel center | C-106 | 16143 | 20,732,000 | 22,790,000 | 43,522,000 |
Electric service facility | C-114 | 16483 | 3,000,000 | 0 | 3,000,000 |
Stadium expansion | C-111 | 16480 | 26,000,000 | 0 | 26,000,000 |
Biomedical Sciences Complex | C-116 | 16485 | 21,864,000 | 0 | 21,864,000 |
| | | | | |
George Mason University | | | | | |
Renovate Student Union Facilities | C-27 | 16123 | 2,500,000 | 0 | 2,500,000 |
| | | | | |
Virginia Community College System | | | | | |
Construct downtown campus parking deck, J. Sargeant Reynolds | C-93 | 16345 | 4,500,000 | 1,980,000 | 6,480,000 |
| | | | | |
Christopher Newport University | | | | | |
Renovate Student Center | C-18 | 16346 | 4,385,000 | 0 | 4,385,000 |
Track Renovations | C-19.30 | 16519 | $2,500,000 | 0 | $2,500,000 |
Athletics Expansion | C-19.40 | 16520 | $4,300,000 | $0 | $4,300,000 |
| | | | | |
James Madison University | | | | | |
Bridgeforth Stadium | C-29 | 16396 | $4,000,000 | $12,076,000 | $16,076,000 |
| | | | | |
TOTAL FOR NONGENERAL OBLIGATION BONDS 9(D) | | | $125,532,000 | $30,843,000 | $156,375,000 |
| | | $196,932,000 | $72,092,000 | $269,024,000 |