Page 589, after line 37, insert:
"A.1. Capital projects authorized for detailed planning in § 1 of the third enactment clause of Chapter 1 and Chapter 2 (2008 Special Session I) may proceed from preliminary working drawings to detailed working drawings.  
2. Such nongeneral funds as may be required for this purpose are hereby appropriated.
3. Nongeneral funds expended for the purposes of paragraphs A.1 and A.2 of this Item may be reimbursed from such funds as may be appropriated for the construction of the project for which planning is undertaken, upon project completion."


Explanation
(This amendment allows projects authorized for planning in the 2008 capital bond bill to continue planning with nongeneral funds.)