Language Page 483, after line 11, insert:"C-55.30 Construction: Equipment Supplement for Gornto Teletechnet Center (15519) $1,200,000 Fund Sources: General $1,200,000".
Explanation(This amendment provides a $1.2 million general fund supplement for fixed equipment in the Teletechnet facility, which is currently under construction. Funds of $3.0 million were budgeted in the project [total cost of $12.6 million], but the lowest bids received on the equipment were $4.3 million.)