|  | First Year - FY2009 | Second Year - FY2010 | Totals | 
|---|
|  Office of Public Safety | $96,812,000 | $8,996,000 |  | 
|---|
|  Department of Forensic Science | $3,827,000 | $0 |  | 
| C-114 | New Construction:  Expand Laboratory Space in Norfolk Forensic Lab Building | $3,827,000 | $0 |  | 
| C-115 | Language Only |  |  | 
|  Department of Alcoholic Beverage Control | $400,000 | $400,000 |  | 
| C-115.10 | Maintenance Reserve | $400,000 | $400,000 |  | 
|  Department of Corrections | $47,339,000 | $6,700,000 |  | 
| C-116 | New Construction:  Construct New Dairy and Dairy Processing Center | $7,178,000 | $0 |  | 
| C-117 | New Construction:  Medium Security Correctional Facility, Mount Rogers Planning District | $4,000,000 | $1,700,000 |  | 
| C-118 | Improvements:  Powhatan Electrical System Upgrade | $2,000,000 | $0 |  | 
| C-119 | Improvements:  Install Fire Safety Systems and Exits | $890,000 | $0 |  | 
| C-120 | New Construction:  Upgrade Powhatan Wastewater Treatment Plant | $3,812,000 | $0 |  | 
| C-121 | New Construction:  Replace Modular Units at Marion | $4,401,000 | $0 |  | 
| C-122 | Improvements:  Locking Systems and Cell Door Replacement | $2,500,000 | $0 |  | 
| C-123 | Improvements:  Repair/Replace Door Controls | $2,500,000 | $0 |  | 
| C-124 | Equipment:  Install Auger/Grinder Collection Systems | $800,000 | $0 |  | 
| C-125 | New Construction:  Construct New Kitchen and Dining Hall at Halifax | $4,061,000 | $0 |  | 
| C-126 | Improvements:  Replace Sally Port at Southampton | $1,613,000 | $0 |  | 
| C-127 | Improvements:  Replace Plumbing and Heating Systems in Field Units | $2,500,000 | $0 |  | 
| C-128 | Improvements:  Upgrade Electrical Systems, Various Facilities | $600,000 | $0 |  | 
| C-129 | New Construction:  Install Elevated Water Storage Tank at Greensville | $2,771,000 | $0 |  | 
| C-130 | Improvements:  Replace Windows | $2,000,000 | $0 |  | 
| C-131 | Improvements:  Renovate Bathrooms and Provide Handicapped Access at Chesterfield | $500,000 | $0 |  | 
| C-132 | Improvements:  Install Railings and Mesh at Greensville | $622,000 | $0 |  | 
| C-133 | New Construction:  Expand Sally Port Building at Deerfield | $238,000 | $0 |  | 
| C-134 | New Construction:  Upgrade St. Brides Water Treatment Plant | $3,353,000 | $0 |  | 
| C-134.10 | Language Only |  |  | 
| C-134.20 | New Construction:  Craigsville Wastewater Treatment Plant | $1,000,000 | $0 |  | 
| C-134.25 | Improvements:  Replace Roofs Umbrella Project | $0 | $5,000,000 |  | 
|  Department of Emergency Management | $0 | $0 |  | 
| C-135 | Language Only |  |  | 
|  Department of Juvenile Justice | $8,566,000 | $1,704,000 |  | 
| C-136 | New Construction:  Replace Housing Units at Natural Bridge Juvenile Correctional Center | $1,691,000 | $0 |  | 
| C-137 | New Construction:  Replace Classroom Trailers at Beaumont JCCNew Construction:  Replace Classroom Trailers at Beaumont Jcc
 | $450,000 | $0 |  | 
| C-138 | New Construction:  Construct Dry-Storage Warehouse at Culpeper Juvenile Correctional Center | $880,000 | $0 |  | 
| C-139 | Improvements:  Remove Abandoned Underground Fuel Tanks | $250,000 | $0 |  | 
| C-140 | Improvements:  Upgrade Fire Alarm and Protection Systems | $700,000 | $0 |  | 
| C-141 | New Construction:  Replace Natural Gas, Water and Sewage Lines | $2,200,000 | $0 |  | 
| C-142 | Improvements: Upgrade Mechanical, Electrical and Plumbing Systems for Reception and Diagnostic Center Cottages | $700,000 | $0 |  | 
| C-143 | Improvements:  Provide New DCE School HVAC Plant at Hanover Juvenile Correctional CenterImprovements:  Provide New Dce School HVAC Plant at Hanover Juvenile Correctional Center
 | $500,000 | $0 |  | 
| C-144 | Improvements:  Convert Facilities to Propane | $525,000 | $0 |  | 
| C-145 | Improvements:  Connect Cottages to Emergency Generators | $670,000 | $0 |  | 
| C-145.05 | Improvements:  Correct Erosion, Pamunkey | $0 | $1,704,000 |  | 
|  Department of State Police | $25,275,000 | $0 |  | 
| C-146 | New Construction:  Construct A Public Safety Driver Training Facility | $21,400,000 | $0 |  | 
| C-147 | New Construction:  Construct State Police Headquarters Garage | $2,000,000 | $0 |  | 
| C-147.10 | New Construction:  Target Practice RangeNew Construction:  Construct Target Practice Range
 | $1,875,000 | $0 |  | 
|  Department of Veterans Services | $11,405,000 | $192,000 |  | 
| C-148 | Maintenance Reserve | $193,000 | $192,000 |  | 
| C-149 | New Construction:  Construct Southwest Virginia Veterans Cemetery | $11,212,000 | $0 |  | 
| C-150 | Language Only |  |  | 
| C-151 | Language Only |  |  | 
| C-152 | Language Only |  |  | 
| C-153 | Language Only |  |  |