Authority: Title 2.2, Chapter 20.1, Code of Virginia.
A.1. Notwithstanding any other provision of law except the limitations imposed by § 2.2-518, § 2.2-4803 and § 2.2-4806, Code of Virginia, Executive Department agencies and institutions may enter into management agreements with CGI Technologies & Solutions, Inc. (CGI) for debt collection and cost recovery services pursuant to Statements of Work 6 and 7 of the Enterprise Applications Master Services Agreement between the Commonwealth of Virginia and CGI. Executive Department agencies and institutions may also enter into additional Statements of Work with CGI pursuant to § 2.2.4 of the Enterprise Applications Master Services Agreement for services related to such Agreement, which may include, but not be limited to, services supporting projects in the five towers of enterprise-level endeavors (financial management, human resource management, supply chain management, administrative management, and applications development and management).  Work on enhanced collections and recoveries or any additional Statements of Work pursuant to § 2.2.4 of the Enterprise Applications Master Services Agreement shall not proceed if they commit the Commonwealth to expanding or significantly altering any existing federal or state program without the review and approval of the Governor and prior consultation with the Chairmen of the House Appropriations and Senate Finance Committees.
2. Moneys resulting from enhanced collections and cost recoveries pursuant to this Item shall be held in the Virginia Technology Infrastructure Fund as established by § 2.2-2023, Code of Virginia.
3. The Auditor of Public Accounts shall provide the Governor and the Chairmen of the House Appropriations and Senate Finance Committees no later than December 1, 2013, a report of the result of a financial and operational audit of CGI and its subcontractors, as provided in parts 15.2 and 15.3 of the Enterprise Applications Master Services Agreement.  The audit shall review all management agreements between CGI and Executive Department agencies and institutions pursuant to Statements of Work 6 and 7 and include a review of CGI and its subcontractors' performance with regard to measured service levels.
B.1.  As established in § 3-2.03 of this act, working capital advances totaling up to $90,000,000 will provide for the development of enterprise applications for the Commonwealth, including the development of the performance budgeting and financial management systems.  These working capital advances will be repaid from anticipated revenues from enhanced collections, cost recoveries, inter-agency collaborative projects and other initiatives to be collected pursuant to this item and will be deposited into the Virginia Technology Infrastructure Fund.  No funds derived from these working capital advances shall be expended without the prior budget approval of the Secretaries of Technology and Finance.  The State Comptroller shall notify the Governor and the Chairmen of the House Appropriations and Senate Finance Committees prior to any approved expenditure.
2. Funds received from the working capital advance will be used only for enterprise resource planning and development costs. No funds received from this working capital advance shall be used as payment toward operating costs of this or any other program.
3. At the end of each fiscal year, the Governor is authorized to apply up to $2,000,000 from the unappropriated general fund balance in this act to pay down this working capital advance in the event other repayment sources in this act are not available or are insufficient to maintain a reasonable schedule for the payback of the working capital advance.
C.1. In order to minimize the cost of information systems development, the Secretary of Technology shall work with all Cabinet Secretaries and their agencies to develop Commonwealth data standards for citizen-centric data, personnel, recipient information, and other common sources of information gathered by the Commonwealth and in use by systems set out within this item.  Not later than November 1, 2012, the Secretary of Technology shall communicate an initial plan that will provide at least an estimated timetable, cost and description of the anticipated scope of the effort to the Governor and the Chairmen of the House Committee on Appropriations and the Senate Committee on Finance.  A final plan, with a specified timetable and costs required to gather, approve and publish these standards, shall be communicated to the Governor and the Chairmen of the House Committee on Appropriations and the Senate Committee on Finance by July 1, 2013.  In developing the plan, the Secretary of Technology shall use best practices, federal requirements, and existing data standards.  
2. Where active projects in this item, have implemented standardized data, the Secretary of Technology shall work with all Cabinet Secretaries and their agencies to determine if these standards should be adopted as Commonwealth data standards for use in active or future major IT projects or investments.  Where active projects in this item do not conform to the Commonwealth's data standard, the Secretary of Technology shall include in the interim a plan for how the Secretary of Technology will identify data standards that should be adopted as Commonwealth data standards and the estimated cost of ensuring that each active IT project in the item complies with the Commonwealth data standard.
D.1. Notwithstanding the provisions of §§ 2.2-1509, 2.2-2007 and 2.2-2017, Code of Virginia, the scope of formal reporting on major information technology projects in the  Recommended Technology Investment Projects (RTIP) report is reduced beginning in the second year.  The efforts involved in researching, analyzing, reviewing, and preparing the report will be streamlined and project ranking will be discontinued.  Project analysis will be targeted as determined by the Chief Information Officer (CIO) and the Secretary of Technology.  Information on major information technology investments will continue to be provided General Assembly members and staff.   Specifically, the following tasks will not be required, though the task may be performed in a more streamlined fashion:  (i) The annual report to the Governor, the Secretary, and the Joint Commission on Technology and Science;  (ii) The annual report from the CIO for submission to the Secretary, the Information Technology Advisory Council, and the Joint Commission on Technology and Science on a prioritized list of Recommended Technology Investment Projects (RTIP Report);   (iii) The development by the CIO and regular update of a methodology for prioritizing projects based upon the allocation of points to defined criteria and the inclusion of this information in the RTIP Report;  (iv) The indication by the CIO of the number of points and how they were awarded for each project recommended for funding in the RTIP Report;  (vi) The reporting, for each project listed in the RTIP, of all projected costs of ongoing operations and maintenance activities of the project for the next three biennia following project implementation, a justification and description for each project baseline change, and whether the project fails to incorporate existing standards for the maintenance, exchange, and security of data;  and  (vii) The reporting of trends in current projected information technology spending by state agencies and secretariats, including spending on projects, operations and maintenance, and payments to Virginia Information Technologies Agency. 
2. Pursuant to § 2.2-1509.3, Code of Virginia, the following major information technology projects are active and have been approved and recommended for funding by the Secretary of Technology. The data listed was self-reported to the Virginia Information Technologies Agency by the responsible agencies. These projects are supported by strong business cases and thus were considered as priorities for funding in this biennium.
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Social Services (765) -- Automated Child   Care Subsidy System | Jan 11, 2010 |  | $20,364,802 | 
   |  |  | Completed |  | 
   | Implement a Child Care Subsidy Payment System (CCSPS) for   Child Care Subsidies.  The CCSPS will allow for real-time documentation   of attendance and enable the program to better address issues relating to   improper use of subsidies.  |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $0 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Social Services (765) – EDSP –   Eligibility Modernization – MAGI Project | Oct 22, 2012 | Oct 31, 2013 | $22,525,210 | 
   | The Eligibility Modernization Modified Adjusted Gross   Income (MAGI) project will implement a single Medicaid case management system   for MAGI Medicaid and CHIP/FAMIS categories by modifying Virginia Case   Management System (VaCMS) for new applications.  This initiative will   implement a streamlined, secure, and interactive customer experience that   will maximize automation and real-time adjudication while protecting privacy   and personally identifiable information. This enhancement to the Customer   Portal will determine MAGI Medicaid eligibility on-line, perform MMIS   enrollment, perform MMIS disenrollment, access Federal and State verification   systems through Exchanges, and leverage web-services such as the Commonwealth   Authentication Service (CAS) and the Enterprise Data Management (EDM)   solution projects under eHHR. |  |  |  | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $2,305,736 | $768,579 | 
   | Nongeneral Fund | $14,588,173 | $4,862,724 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Social Services (765) – EDSP –   Eligibility Modernization – Program Migration Project | Oct 22, 2012 | Mar 31, 2016 | $75,212,015 | 
   | The modernization and migration consists of MAPPER UNISYS   system replacement for the ADAPT application and the Energy Assistance   Program application.  ADAPT is the current eligibility determination and   case management system for SNAP, TANF, Employment Service.  The   Eligibility Modernization Program Migration Project will convert the cases   that contain the programs in ADAPT and the Energy system into VaCMS along   with accepting new applications for these programs via online (Customer   Portal) and paper (manual data entry) processes.  This project also   involves the external rules engine (iLOG).  All program rules will be   incorporated into iLOG with the outcome of eligibility determination,   authorization, and case management within this single case management solution. |  |  |  | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $2,924,187 | $5,848,374 | 
   | Nongeneral Fund | $8,646,892 | $17,293,784 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Social Services (765) – EDSP –   Eligibility Modernization – Conversion | Nov 13, 2012 | Apr 30, 2015 | $10,583,249 | 
   | The EDSP Eligibility Modernization Conversion project will   focus its efforts on converting the data in the ADAPT legacy system and DMAS   CHAMPS legacy system for the Families & Children's Medicaid, CHIP, and   FAMIS categories into VaCMS.  The CMS federal requirement stipulates for   these eligible ongoing Medicaid categories (staring April 2014) at the time   of their renewal process, continued eligibility must be evaluated against the   new MAGI Medicaid rules.  This conversion project will move those   existing cases into VaCMS and eligibility determination be performed by the   external rules engine accomplished in the Eligibility Modernization MAGI   project.  Conversion will be performed on a month by month schedule   (based on the Medicaid renewal date) until all cases for these categories   have been converted from these two legacy systems. |  |  |  | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $297,654 | $892,962 | 
   | Nongeneral Fund | $2,348,158 | $7,044,475 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Accounts (151) -- Cardinal Project | Apr 17, 2008 |  |  | 
   |  |  | Completed | $58,337,353 | 
   | The Department of Accounts is replacing its statewide general   ledger system- CARS.   The new system will serve as the   Commonwealth's general ledger system of record.  The functional scope of   the project includes General Ledger, Cash Receipting, and Cash Disbursement,   which is considered the Enterprise Base System.  This project consists   of roll-out of the base application to replace the Virginia Department of   Transportation's (VDOT) FMS II system, roll-out of the Enterprise Base System   at the Department of Accounts Fiscal Office, and statewide roll-out to all   agencies of the Enterprise Base System, replacing CARS as the Commonwealth's   general ledger system.  Estimated project cost includes VDOT costs. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund |  |  | 
   |  | $164,978 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Professional and Occupational Regulation   (222) -- EAGLES | Mar 1, 2007 |  |  | 
   |  |  | Jan 31, 2014 | $7,977,793 | 
   | EAGLES will be a web-enabled application implemented to   replace two legacy systems, CLES and ETS.  EAGLES will also support the   agency's new business requirements.  This project is in line with the   Commonwealth's electronic government initiative, which requires that the   Department be aligned closely with the Digital Signatures and COVA PIN   initiative.   Project Scope:  This project scope includes the   development of the EAGLES web-enabled application to replace the legacy systems,   CLES and ETS, and the expansion of the system to include the Department's new   business requirements.  |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $1,260,600 | $376,500 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Social Services (765) -- EDS - Customer   Portal Enterprise Delivery System Program | Feb 8, 2011 | Sep 14, 2012 |  | 
   |  |  |  | $11,201,779 | 
   | The Enterprise Delivery System Program represents four major   projects: the EDSP Worker Portal, the EDSP Customer Portal, the EDSP Master   Customer ID and the EDSP Document Management Imaging System.  The four   major projects are the foundation for implementing the VDSS vision of a   self-service model that is efficient, effective and provides a streamlined   customer friendly experience.  Within the vision, clients will be able   to file applications for benefits or services through an online application   process, report changes, and manage benefit “accounts” online.   |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $31,499 | $0 | 
   | Nongeneral Fund | $65,501 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Department of Transportation (501) -- Highway   Performance Monitoring System (HPMS) | Sep 1, 2009 |  |  | 
   |  |  | Completed | $1,316,375 | 
   | The Highway Performance Monitoring System (HPMS) supports the   Roadway Network Systems (RNS) program within the Department of Transportation   (VDOT).  The HPMS project includes adding new data fields to RNS for new   data; adding classified public roads to the Highway Traffic Records   Information System (HTRIS); building a user interface to add/edit data in   RNS; and developing a means of managing and creating a file to send all   required data to the Federal Highway Administration (FHWA).   |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund |  | $0 | 
   |  | $35,000 |  | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Department of Transportation (501) – CSC   System 2.0 | Aug 6, 2012 | Jun 30, 2014 | $4,500,000 | 
   | The Customer Service Center Portal 2.0 project will   enhance the functionality and usability of the Customer Service Center   Portal, and will:  Enable Customer Service Center Agents to better   respond to customer inquiries; – Promote VDOT's ability to share information   throughout the agency; and Enhance VDOT's ability to quickly and efficiently   respond to citizen requests for roadway service/ maintenance. |   |   |   | 
   |  |  |  |  |  | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $2,754,340 |  | 
   |  |  | $3,053,060 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Department of Transportation (501) –   Construction Documentation Management | Aug 31, 2012 | Jun 28, 2013 | $1,100,000 | 
   | This project is to implement a consistent way of managing construction   documents, and in particular electronic documents, across all districts.    Part of this initiative is to also to automate the Advertisement and   Award process workflow to optimize its document management during the initial   stages of the construction management lifecycle. |   |   |   | 
   |  |  |  |  |  | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $1,100,000 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Department of Transportation (501) – Snow   Plowing Tracking | Oct 12, 2012 | May 31, 2014 | $5,220,380 | 
   | The scope of the Snow Plow Tracking Project is to provide a   comprehensive approach for VDOT to manage its snow plowing tracking   initiative across the entire Commonwealth. VDOT intends to provide snow   plowing tracking and display for operational use and public consumption   statewide on all VDOT managed roadways at the street level. The Department   also wishes to improve customer services and transparency of services being   provided across the Commonwealth and improve internal business operations   across the enterprise. |   |   |   | 
   |  |  |  |  |  | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $2,805,760 | $2,414,620 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Medical Assistance Services (602) -- HIPAA   Upgraded Transactions (5010/NCPDPD.0) | Apr 19, 2011 |  |  | 
   |  |  | Completed | $1,446,945 | 
   | The Centers for Medicare and Medicaid Services (CMS) has proposed   regulations requiring that all X12 Transactions be upgraded to the 5010   versions and that the ICD-10 version of the code sets be implemented.    DMAS must implement the new versions in order to remain HIPAA compliant and   continue to receive and send electronic eligibility, claims, and payment data   with approximately 50,000 providers and 300 plus service centers.    Implementation of the changes will require modification to the MMIS and   extensive provider outreach and trading partner testing. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  | $0 | 
   |  | $212,525 |  | 
   | Nongeneral Fund |  | $0 | 
   |  | $1,234,420 |  | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Medical Assistance Services (602) – ACA –   NCCI (National Correct Coding Initiative) | Sep 28, 2012 | Jul 31, 2013 | $1,539,247 | 
   | In accordance with the implementation of the Patient Protection   and Affordable Care Act of 2010 and as amended by the Health Care and   Education Recovery Act of 2010 (known together as the Affordable Care Act),   the Virginia Department of Medical Assistance Services is conducting a   project to comply with the Mandatory State Use of National Correct Coding   Initiative (NCCI). |   |   |   | 
   |  |  |  |  |  | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $160,111 | $0 | 
   | Nongeneral Fund | $1,379,136 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia State Police (156) -- Law Enforcement Activity   Management System | Jun 13, 2007 |  |  | 
   |  |  | Feb 15, 2013 | $3,421,600 | 
   | The LEAMS project will provide a comprehensive system to   support the documentation of criminal investigations and related law   enforcement activities and reduce the agency's dependence on burdensome   paper-based workflows and difficult-to-change legacy technologies.  The   system will make use of up-to-date technology to upgrade process controls,   management/supervisory oversight, data quality, processing timeliness, system   access, analytical tools, and intra-agency and inter-agency cooperation   needed to maintain quality law enforcement records as mandated under §   15.2.-1722 of the Code of Virginia. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $13,200 | $0 | 
   | Nongeneral Fund | $712,000 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia State Police (156) – AFIS Upgrade to Integra –   Phase 1 | Jan 18, 2012 | Nov 18, 2012 | $1,010,354 | 
   | Upgrade the current AFIS system hardware and software with   a new NEC Integra ID system.  This new system will be installed at the   VSP central site and will offer added flexibility in the automated workflow   options and specifications.  The proposed redundant hardware solution   will offer improved Disaster Recovery possibilities.  The proprietary   hardware matchers will be replaced with off-the-shelf hardware and software   matching.  Phase 1:   Phase 1 of the project will include the new   functionality for Mobile ID identifications and responses and submission of   the searches to the FBI Repository of Individuals of Special Concern (RISC).    This will require the current database to be converted to the new   Automated Biometric Identification System (ABIS) format.  New hardware   is needed to support the new functionality and the new database. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $0 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Behavioral Health and Developmental Services   (720) -- Medication Management System:  Pharmacy Systems Software   Application | Oct 6, 2008 |  | $3,500,000 | 
   |  |  | Completed |  | 
   | The Medication Management System will replace the legacy   pharmacy system with an integrated medication management application sharing   an electronic medical record repository.  The scope of the project   is to implement a medication management system that utilizes an electronic   medical record repository at each DBHDS facility.  The project would   replace legacy systems and integrate with recent IT investments such as   AVATAR for patient/resident admissions, discharges, and reimbursements.    The project would also replace the outdated In-Patient and Aftercare pharmacy   systems. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $0 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Planning and Budget (122) -- Performance   Budgeting Solution | Jul 24, 2009 |  |  | 
   |  |  | Completed | $15,000,312 | 
   | The project is the implementation of a performance budgeting   system to replace the current budgeting and strategic planning applications   (PROBUD, WebBEARS, Budgetwise and Expendwise).  Today the Commonwealth's   strategic planning and budget development processes use a wide range of   disparate systems.  These systems have limited integration and   interfacing capabilities.  The Commonwealth currently relies on numerous   systems, applications, and processes to support the Performance Budgeting   business process.   |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund |  | $0 | 
   |  | $1,842,283 |  | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Corrections (799) -- Phase 2 and 3 Virginia   Correctional Information System (CORIS) | Jun 22, 2006 |  |  | 
   |  |  | Nov 30, 2012 | $23,093,458 | 
   | The Department of Corrections (DOC) has established an automated   Offender Management Information System (OMS) Program, now called   VirginiaCORIS.  This is a major technology effort and is critical to the   successful accomplishment of the DOC mission.  The VirginiaCORIS Program   will be composed of multiple major projects, and will result in a single,   fully integrated system that should replace most of the DOC's current   offender-related application portfolio.  The selected solution is   already in production in other state DOCs, with some additional required functionality   being developed and planned for deployment in the next 12 months.  |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  | $0 | 
   |  | $1,176,100 |  | 
   | Nongeneral Fund | $0 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Department of Transportation (501) -- Roadway   Inventory Management System | Jan 1, 2010 |  | $ | 
   |  |  | Aug 30, 2013 | $4,995,000 | 
   | The Roadway Inventory Management System (RIMS) supports the   Roadway Network Systems (RNS) program within the Department of Transportation   (VDOT).  RIMS involve a process redesign that will assist RNS in providing   road inventory and attribute data on Straight Line Diagrams (SLDs) and   maps.  The current process and systems for capturing roadway inventory   data are slow, inefficient and do not portray an accurate picture of the   ground truth.  No mapping capability is present today.  Upon   completion, RIMS will support RNS in providing streamlined business   processes; timely updates to inventory; advanced inventory query and   reporting; enhanced mapping functions; improved performance; and eliminate   duplicate data entry for road inventory within the Database for Administering   Changes in VDOT Highway Systems (DACHS) application. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $0 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Education (201) -- State Longitudinal Data   System (SLDS) | Feb 16, 2011 |  | $13,522,897 | 
   |  |  | Sep 30, 2013 |  | 
   | The Virginia Department of Education (VDOE) —in partnership   with the Office of the Governor, the State Council of Higher Education   (SCHEV), the Virginia Community College System, the Virginia Information   Technologies Agency, and Virginia's workforce agencies—proposes to expand on   the advancements we have made through our current Statewide Longitudinal Data   Systems (SLDS) grant.  |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $3,002,565 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Employment Commission (182) -- Unemployment   Insurance Modernization | Sep 17, 2009 |  |  | 
   |  |  | Sep 11, 2014 | $58,540,155 | 
   | The VEC needs to modernize the Unemployment Insurance   Benefits and Tax (UIBT) system.  The current system is based on VEC   priorities identified in the mid-1980s.  Since that time, the statutory environment   and the business processes have changed.  The current UIBT system is   difficult to upgrade and costly to maintain when compared to systems that are   available in today's market.  As a result of these concerns, VEC has   identified two goals for the Unemployment Insurance Modernization Project:   ·Replace the existing UIBT applications using a foundation of new technology   and improved design methods to improve flexibility and maintainability.  |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $14,594,530 | $8,052,200 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Department of Transportation (501) -- VGIN/VDOT Road   Centerline Transition Project | Jun 15, 2010 |  | $1,053,521 | 
   |  |  | Completed |  | 
   | The Commonwealth of Virginia has established the goal that   for each type of data there will be a single source system of record.  In   addition, the Commonwealth Chief Information Officer (CIO) has mandated that   the Roadway Network System (RNS) migrate to and use the enterprise road   centerlines (E-RCL) maintained by the Virginia Geographic Information Network   (VGIN).  This project supports achievement of both goals by addressing   two main business problems:  1) the existence of multiple sources of   road centerline (RCL) data, and 2) the duplication of effort required to   maintain these multiple data sets. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $0 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Health (601) -- Women, Infants, Children (WIC)   Electronic Benefits Transfer (EBT) Project | Jan 8, 2009 |  |  | 
   |  |  | Aug 26, 2013 | $6,619,018 | 
   | The Women, Infants, and Children (WIC) Electronic Benefits Transfer   (EBT) Project will develop and implement the business processes and   associated technology to provide electronic WIC (e-WIC) issuance, redemption,   payment, and reconciliation services to distribute food benefits in the   Virginia WIC Program.  The manual, paper-based system introduces   numerous inefficiencies into the process.  The project will require   procurement of a number of services including support for the development of   an Implementation Advanced Planning Document (IAPD), as required by the United   States Department of Agriculture Food and Nutrition Service, Quality   Assurance and Monitoring, and Design, Development, and Implementation of the   selected e-WIC solution.  The project will implement an online,   outsourced EBT technology.   |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $802,075 | $21,713 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Information Technologies Agency (136) --   Commonwealth Enterprise Data Management (EDM) | Sep 1, 2011 |  |  | 
   |  |  | Jun 21, 2013 | $7,625,177 | 
   | The Health and Human Resources (HHR) Secretary and the Commonwealth's   MITA Program Manager have requested that the Virginia Information   Technologies Agency (VITA) provide an enterprise data management solution   that will store enterprise data and facilitate data sharing at an enterprise   level. The Secretary, in collaboration with the Secretary of Technology, is   leading the Commonwealth's efforts to improve and modernize the Medicaid   program's information technology infrastructure.  |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  | $0 | 
   |  | $64,132 |  | 
   | Nongeneral Fund |  | $0 | 
   |  | $577,000 |  | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Information Technologies Agency (136) -- Commonwealth   Service Oriented Architecture | Sep 21, 2011 |  |  | 
   |  |  | Nov 29, 2013 | $11,756,392 | 
   | This program created the Commonwealth Service Oriented   Architecture Project to provide the necessary infrastructure and governance. As   such, the project shall procure, install, and configure the software and   hardware necessary to establish test, production, and disaster recovery   environments. In addition, the project shall institute an appropriate Center   of Competence and related governance. Finally, in concert with the   Commonwealth Enterprise Data Management (EDM) Project, this project shall   develop and deploy the web services for the Commonwealth's EDM solution. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  | $0 | 
   |  | $68,080 |  | 
   | Nongeneral Fund |  | $0 | 
   |  | $612,724 |  | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Information Technologies Agency (136) – Telecommunications   Expense (Management) and Billing Systems (TEBS) | May 1, 2013 | Mar 31, 2015 | $3,000,000 | 
   | The Telecommunications Expense (Management) and Billing   System (TEBS) project will procure and implement a modern, integrated, user-friendly   telecommunications expense management and billing solution. The TEBS project   is for the Virginia Information Technologies Agency (VITA).  The goal of   the TEBS project is to replace the 30+ year-old mainframe Telecommunications   Inventory Billing System (TIBS) that currently supports VITA's   Telecommunications Service Delivery with a modern integrated, user-friendly   system that supports all of the existing TIBS functionality and providing   additional telecommunication expense functionality. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $0 | $1,820,000 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Department of Transportation (501) -- Urban  Conversion Project | Oct 11, 2010 | Dec 12, 2013 | $2,722,535 | 
   | VDOT is required to submit annual reports to the Federal Highway   Administration as part of the Highway Performance Monitoring System   (HPMS).  To expedite the generation of these reports, VDOT desires to   generate a Linear Referencing System based on both local government roadway   information and Virginia Geographic Information Network (VGIN) urban data   set.  This project will consolidate the local data, the VGIN data and   VDOT's data into a single set. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $1,142,785 | $329,300 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Health (601) -- Electronic Death   Registration (EDR) | Mar 22, 2011 | Dec 30, 2014 | $3,003,500 | 
   | The Electronic Death Registration (EDR) system is a proposed   web-based system that would allow for the electronic capture of death data   from funeral service licensees, state medical examiners and state   physicians.  The system would allow the VDH Division of Vital Records   (DVR) and local health departments to issue and retain death certificates   electronically as opposed to the manual process that is currently used.    The Electronic Death Registration system is expected to reduce reporting   delays, improve data quality, and increase the utility of death data. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $880,500 | $421,666 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Employment Commission (182) -- Financial   Management System | Aug 18, 2011 |  |  | 
   |  |  | Dec 31, 2013 | $4,948,456 | 
   | The Financial Management Accounting System will replace the current   mainframe batch system.  The new system will include modules for   accounts payable, accounts receivable, general ledger, cost allocation, time   distribution and procurement. Financial data will be processed in an on-line,   real-time environment.  These features will greatly improve efficiency   in financial processes, availability of management information, and the   accuracy of accounting reports, thus reducing the potential for audit   findings. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund |  |  | 
   |  | $2,495,500 | $1,855,196 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Motor Vehicles (154) -- DMV CSI Systems   Redesign - Development and Implementation | Nov 15, 2010 |  | $69,954,521 | 
   |  |  | Cancelled |  | 
   | The CSS Redesign focuses on the fragmented processing of   DMV's three major business areas:  driver, vehicle, and motor   carrier.  The purpose of the redesign is to transform these fragmented   fifteen year old systems into one modernized system that is responsive to the   ever-changing needs relating to internal security, homeland security, legislative   mandates, and customer relationship management.  DMV has a unique   opportunity to revolutionize the agency's approach to fulfilling its mission,   carrying out core functions, and delivering service.  DMV intends to   fully integrate processing while incorporating and leveraging the full   functionality and benefits of proposed technology solutions as well as the   technology already in place. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $22,663,410 | $2,658,663 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Motor Vehicles (154) -- DMV FACE – DMV   Correspondence Transformation | Aug 15, 2012 | Jun 30, 2013 | $1,382,400 | 
   | DMV issues an average of 30,000 pieces of correspondence   weekly (1.56 million annually), many of which are required by Virginia Code.    The current solution for developing and modifying correspondence has   reached its end of life and is no longer supported.  It requires   professional IT resources for every change.  This FACE sub-project will   replace all existing correspondence and transform the business logic which   drives it. The resulting solution will allow business owners to self-service   correspondence and play an expanded role in the creation of new artifacts. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $1,382,400 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Secretary of Health and Human Resources (188) -- Birth   Reporting Interface (BRI) | Dec 30, 2011 |  |  | 
   |  |  | Sep 30, 2014 | $2,112,000 | 
   | This project will establish a birth reporting service/interface   between the birth registry and the ESB.  The system of record for all   birth records will be VVESTS (Virginia Vital Events and Screening Tracking   System).  The proposed functionality must support a HITSAC approved data   standard which should align with the EDM standards.  The project   requires use of HITSAC endorsed messaging standards. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  |  | 
   |  | $71,280 | $142,560 | 
   | Nongeneral Fund |  |  | 
   |  | $562,320 | $1,124,640 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Motor Vehicles (154) -- Commonwealth   Authentication Services | Dec 18, 2011 |  |  | 
   |  |  | Jun 24, 2013 | $4,408,762 | 
   | Through the collaboration of the Technology, Health and Human   Resources, and Transportation secretariats, on-line identity authentication   services will be built for all Commonwealth agencies to use.  The Commonwealth   Authentication Services (CAS) project will implement a COTS project with the   assistance of an implementation partner so that DMV, DSS, DMAS and the Health   Information Exchange (HIE) can all leverage a common authentication system   for users to gain access to selected customer-facing systems.  The CAS   system will be hosted, operated and maintained by VITA as a shared service,   and participating agencies will pay to use CAS.  Once CAS is fully   operational, additional agencies will be encouraged to convert over from   their own point-solutions to CAS. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  | $0 | 
   |  | $389,876 |  | 
   | Nongeneral Fund |  | $0 | 
   |  | $3,508,886 |  | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Motor Vehicles (154) – FACE – Motor   Carrier Portal Phase 1 | Dec 15, 2013 | Dec 31, 2013 | $1,797,120 | 
   | DMV has a highly sophisticated Motor Carrier operation that   manages every aspect of driver and vehicle licensing, fuels tax, inter- and   intra-state regulations and licensing. The Motor Carrier work centers operate   in a mixed application environment with outdated systems. DMV's commercial   carrier customers also interface with DMV through up to three different   systems depending upon the transaction.  Each of the systems is at   end-of-life.  Among the key business strategies for the agency, is the   recruitment of additional Motor Carrier customers.  DMV has attracted   several Top 100 carriers to Virginia in the past year representing millions   in revenue and is need of system updates to remain competitive.  Thus,   the need to develop a single-point of entry for all Motor Carrier customers'   needs. |  |  |  | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $898,560 | $898,560 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Secretary of Health and Human Resources (188) -- Death   Reporting Interface (DRI) | Dec 30, 2011 |  |  | 
   |  |  | Sep 30, 2014 | $2,112,000 | 
   | This project is designed to establish a death reporting   service/interfaces between the death registry and the ESB.  The service   will be supported by an extract of the minimum required fields to identify a   death record.  Additional development may be required to add a match   code (Yes/No) and an MPI placeholder. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  |  | 
   |  | $71,280 | $142,560 | 
   | Nongeneral Fund |  |  | 
   |  | $562,320 | $1,124,640 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Secretary of Health and Human Resources (188) –   HIT/MITA Program | Nov 14, 2011 | Apr 29, 2014 | $53,373,320 | 
   | The purpose of the HIT/MITA Program is to align the Commonwealth   with Federal direction relative to the American Recovery and Reinvestment Act   (ARRA) and the Patient Protection and Affordable Care Act of 2010 (PPACA).   These acts present significant funding opportunities to improve the quality   and value of American healthcare. PPACA mandates Medicaid expansion in 2014,   which is predicted to increase Virginia's Medicaid membership by 35-45%.   Leveraging the Federal funding opportunities to offset the impact of   expansion is an important investment in Virginia's future. The Federal   funding available under ARRA and PPACA provide opportunities to achieve the   following outcomes for Virginia; Build on current health reform efforts;   Modernize information technology infrastructure as an enabler for future   business transformation; Provide a technical environment where   standards-based interoperability is possible between new and legacy systems;   Provide web based self-directed service options for human services; Reduce   the need for large administrative and operational staff for Federal and State   programs; Reduce overall long-term technology costs for Federal and State   programs; and Provide an enterprise technology environment that is accessible   on a pay-for-use basis by Federal, State, and local governments as well as   non-government organizations, community based-services, and commercial   interests as allowed by policy. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $704,245 | $603,304 | 
   | Nongeneral Fund | $3,387,170 | $2,848,475 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Medical Assistance Services (602) -- DMAS   Eligibility System Support | Jul 30, 2012 |  | $4,871,340 | 
   |  |  | Cancelled |  | 
   | The Patient Protection and Affordable Care Act (ACA) require   a Medicaid population expansion that will occur in 2014.  Along with the   expansion a Health Insurance Exchange and a standardization of enrollment   forms across all health & human services programs will also take   place.  The DMAS Eligibility System Support project will provide the   needed support to the contractor for the replacement of the eligibility   systems. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $443,292 | $189,9820 | 
   | Nongeneral Fund | $2,966,646 | $1,271,420 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Behavioral Health and Developmental Services   (720) -- Electronic Health Records (EHR) | Dec 30, 2011 |  |  | 
   |  |  | Jun 30, 2015 | $34,256,000 | 
   | The Clinical Apps/EHR project will replace legacy systems   with integrated clinical applications sharing an electronic medical record repository.    The scope of the project is to implement an electronic medical record   repository and clinical applications at each DBHDS facility and Central   Office.  The project would replace legacy systems and integrate with   recent IT investments such as AVATAR for patient/resident admissions,   discharges, and reimbursements. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  |  | 
   |  | $4,380,000 | $1,900,000 | 
   | Nongeneral Fund |  |  | 
   |  | $12,000,000 | $8,500,000 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Secretary of Health and Human Resources (188) --   Electronic Lab Reporting Interface (ELRI) | Dec 30, 2011 | Dec 2, 2012 | $2,074,248 | 
   | Clinical laboratories throughout Virginia (including DGS   Department of Consolidated Laboratory Services (DCLS) and national clinical   reference laboratories submit reportable disease findings to VDH. Test orders   are submitted to DCLS and DCLS returns test results. Current partners include   VDH and a growing number of Virginia hospitals.  Additional legacy   formatted exchanges between DCLS and VDH will continue until they are   converted to HL7, but the legacy messages will not be managed through the   interface.  This project interfaces DCLS interfaces to the   Commonwealth's Enterprise Service Bus (ESB) for access by the Health   Information Exchange. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $107,861 | $0 | 
   | Nongeneral Fund | $721,838 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Accounts (151) -- Financial Management   Enterprise Rollout (Cardinal Project Part 3) | Jul 1, 2012 |  | $56,991,880 | 
   |  |  | Mar 1, 2015 |  | 
   | This project will replace the Commonwealth's (Department of   Accounts) current financial system, Commonwealth Accounting and Reporting   System (CARS).  It will be an Enterprise Resource Planning (ERP)   implementation of General Ledger and Accounts Payable, the two accounting   features currently contained within CARS.  The system will be deployed   to all current day CARS users and interfaced with the financial systems that   currently interface to CARS.  The scope of this project also includes   the Change Leadership and Training required to migrate off of CARS. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $22,333,480 | $29,903,680 | 
   | Nongeneral Fund | $0 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Department of  Transportation   (501) -- FMS Sun Set and Data Marts | Sep 1, 2011 |  |  | 
   |  |  | Mar 15, 2013 | $1,820,000 | 
   | The implementation of the Cardinal Project will necessitate   the sun setting of both the FMSI and FMSII Financial Systems and retention of   business critical data.  Sun Setting of these systems in an organized   fashion will create greatly reduced operational expenses from VITA.  The   FMS Data Marts will retain critical data from the FMSI and FMSII Financial   Systems and create a Financial Data Store for reporting purposes.  The   objective of this project is to have the data store information available to   VDOT internal systems to merge with Cardinal financial data for business   intelligence reporting. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund |  | $0 | 
   |  | $1,005,000 |  | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Medical Assistance Services (602) -- HIPAA   Upgrade Code Set (ICD010) | Dec 15, 2011 |  |  | 
   |  |  | Feb 14, 2014 | $9,872,529 | 
   | The Centers for Medicare and Medicaid Services (CMS) has   proposed regulations requiring that all X12 Transactions be upgraded to the   5010 versions and that the ICD010 version of the code sets be   implemented.  DMAS must implement the new versions in order to remain   HIPAA compliant and continue to receive and send electronic eligibility,   claims, and payment data with approximately 50,000 providers and 300 plus   service centers.  Implementation of the changes will require   modification to the MMIS and extensive provider outreach and trading partner   testing. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  |  | 
   |  | $1,051,700 | $141,441 | 
   | Nongeneral Fund |  |  | 
   |  | $6,217,280 | $1,003,907 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Motor Vehicles (154) -- KATS II:  Next   Generation Knowledge Automated Testing System | Jun 15, 2012 |  |  | 
   |  |  | Dec 1, 2013 | $1,944,693 | 
   | The Virginia Department of Motor Vehicles seeks to acquire a   turn-key contract, through competitive negotiation, for the acquisition,   design, custom development, installation, training, and maintenance of a   network of Knowledge Automated Testing Systems (KATS) on a firm fixed price   basis. The KATS system will be installed in all DMV Customer Service Center   locations and mobile Customer Service Centers throughout the Commonwealth as   specified by DMV.  This project will replace the current KATS system   with one incorporating necessary advancements in testing and technology which   were not available when the current KATS was implemented in 1993 and updated   in 2005. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund |  |  | 
   |  | $1,868,298 | $76,395 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Secretary of Health and Human Resources (188) --   Immunization Registry Interface (IRI) | Dec 30, 2011 |  | $ | 
   |  |  | Sep 30, 2014 | $1,808,000 | 
   | Participating organizations such as hospital providers create   a file to include new and updated immunization activity for import into   Virginia Immunization Information System (VIIS) and receive an   acknowledgement of their transmission from VIIS. All content processing and   data de-duplication will be performed by VIIS. Business partners may also   create a query message to which VIIS will generate a response message. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  |  | 
   |  | $54,240 | $108,480 | 
   | Nongeneral Fund |  |  | 
   |  | $488,160 | $976,320 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Department of Transportation (501) -- Inventory   Module (Cardinal) | Jan 1, 2012 |  | $4,900,000 | 
   |  |  | Dec 31, 2013 |  | 
   | Replace the software technology for the Web IMS application.   The current WebIMS application technology is reaching the end of its   productive life. Microsoft Corporation stopped supporting this classic Active   Server Pages software in 2008 and it is not possible to make changes to   certain sections of the application. This project will also encompass ITD   activities supporting the data exchanges between the Inventory Management   System (IMS) and the Cardinal Project FMS.  This effort includes   interface design review, data mapping and validation, analysis, and Financial   Planning Division and Cardinal Project support activities carried out by ITD   related to this effort.  Currently several potential data exchange   processes (interfaces) have been defined.  Analysis and design tasks   will define final scope of effort.  |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $4,000,000 |  | 
   |  |  | $900,000 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Department of Transportation (501) -- Maintenance   Infrastructure Management System | Sep 1, 2011 | Aug 1, 2014 | $4,879,112 | 
   | Replace the existing Asset Management System which is no   longer adequate for the increased demand for information sharing that has   come into being over the last few years.  The current system does not   support many needed functions for use, which makes it more labor intensive   and error prone than the Agency can tolerate in this environment.  It   was designed to be a standalone system, and now there are requests for the   data contained within.  The 'Blueprint' activities over the last year   and resulting reduction in force have left VDOT with more to do with less   people. The need for more efficient and reliable system is needed. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $1,931,948 | $178,468 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of State Police (156) -- Replacement and   Enhancement of the Central Criminal History (CCH) Application | Jul 9, 2012 | Dec 31, 2015 | $6,500,000 | 
   | The Centralized Criminal History (CCH) application is a   component of the larger Central Criminal Records Exchange (CCRE)   system.  CCH is more than 30 years old, and many of its capabilities are   based on a proprietary emulation package, which limits the Virginia State   Police (VSP) ability to use the updated infrastructure on which it   resides.  The project includes purchasing of consulting services to   gather requirements and develop an implementation plan for either the   replacement or enhancement of the CCH system.  Once the requirements   have been gathered, the agency will survey the market to determine whether a   suitable commercial off the shelf (COTS) package exists or whether   development will be necessary.  The project also includes planning for   implementation of the system, including installation and deployment of the   software at VSP and training services for VSP staff and local agencies. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund |  |  | 
   |  | $2,000,000 | $2,000,000 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of State Police (156) -- Replacement and Enhancement   of the Statewide Incident Based Reporting System | Jul 9, 2012 |  | $1,200,000 | 
   |  |  | Dec 31, 2014 |  | 
   | The project will either replace or enhance the current   statewide IBRS which operates on legacy technology and does not meet the needs   of the law enforcement community in Virginia.  Consulting services will   be used to gather the requirements for the target system.  Once the   requirements have been gathered, the agency will survey the market to   determine whether a suitable commercial off the shelf (COTS) package exists,   or whether development will be necessary.  The project also includes   planning for implementation of the system, including installation and   deployment of the software at Virginia State Police (VSP), and training services   for VSP and the local agencies. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund |  |  | 
   |  | $200,000 | $500,000 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Secretary of Health and Human Resources (188) -- Rhapsody   Connectivity (RC) | Dec 30, 2011 |  |  | 
   |  |  | Sep 30, 2014 | $1,656,000 | 
   | The Orion Rhapsody data integration engine is used by DGS Department   of Consolidated Laboratory Services (DCLS) and VDH to facilitate the accurate   and secure exchange of electronic data using with the COV Enterprise Service   Bus (ESB). VDH and DCLS interfaces use Rhapsody for messaging. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  |  | 
   |  | $49,680 | $99,360 | 
   | Nongeneral Fund |  |  | 
   |  | $447,120 | $894,240 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Virginia Department of Transportation (501) -- SharePoint   2010 | Jan 20, 2011 |  | $1,914,944 | 
   |  |  | Completed |  | 
   | An upgrade will be made to the agency intranet ‘InsideVDOT' currently   powered by Microsoft SharePoint 2003 software. Since the current software has   not been supported since 2009, an upgrade to Microsoft Office SharePoint   Server 2010 is necessary to support the added functionality. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $0 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of State Police (156) -- STARS Asset Management   Tracking System | May 14, 2012 |  | $1,020,000 | 
   |  |  | Jun 30, 2014 |  | 
   | The Statewide Agencies Radio System (STARS) Program needs an asset   management and tracking system to provide up to date inventory information   and historical tracking of radio and tower assets and equipment.    Motorola, under the terms of the STARS contract, provides an inventory system   for VSP's STARS equipment. This inventory system does not provide timely   information on the STARS assets and inventory. Nor does it provide historical   tracking of assets. In addition, once 60,000 items are in the inventory,   Motorola's charges for the system will greatly increase.  Currently, VSP   has over 40,000 items in inventory. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund |  |  | 
   |  | $460,000 | $560,000 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Secretary of Health and Human Resources (188) -- Syndromic   Surveillance Interface (SSI) | Dec 30, 2011 | Dec 2, 2012 | $2,639,952 | 
   | Participating organizations create a file to include data transmitted   to the Virginia Department of Health (VDH) from facilities on a daily   basis.  The data is grouped into syndromes and statistical algorithms   and are run to identify unusual temporal and geographic patterns that might   indicate situations of concern. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $34,319 | $0 | 
   | Nongeneral Fund | $229,676 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Taxation (161) --  Telephone   Replacement with VOIP | Dec 30, 2011 |  |  | 
   |  |  | May 1, 2013 | $2,100,000 | 
   | This project will replace the Department's current phone   system components with VOIP.  This will allow the agency to eliminate   its Rockwell Phone System and adhere with VITA strategic direction. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  | $0 | 
   |  | $937,000 |  | 
   | Nongeneral Fund | $0 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Human Resource Management (129) -- Time,   Attendance, and Leave (TAL) | Dec 16, 2011 | Oct 31, 2013 | $966,739 | 
   | TAL is a manual process for most Commonwealth agencies. The   responsible stewardship of state resources demands the adoption of a modern   approach to TAL. This project will automate an intensely manual process and   thereby create efficiencies and improvements in and provide statewide   economies of scale for the time and leave accounting process. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund | $0 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of State Police (156) -- Virginia Intelligence   Management System (VIMS) | Jan 3, 2012 |  |  | 
   |  |  | Jun 28, 2014 | $2,500,000 | 
   | In 2005, the Virginia Fusion Center (VFC) was formed within   Virginia State Police to focus on counter terrorism intelligence   investigations and analysis.  The VFC is a joint operation between VSP   and the Virginia Department of Emergency Management (VDEM).  VSP   currently operates a system for statewide intelligence, Tactical Intelligence   Processing System (TIPS).  VSP plans to replace and enhance the TIPS   system since it is based on proprietary technology (Mapper) and has limited   functionality. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund |  |  | 
   |  | $1,000,000 | $1,500,000 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Department of Corrections (799) -- Virginia CORIS   Integration with LIDS (Local Inmate Data System) | Nov 1, 2011 |  |  | 
   |  |  | Jun 30, 2013 | $2,240,480 | 
   | The LIDS system records offenders who enter and exit jail for   purpose of funding per diem costs in these facilities.  This project   will enhance the existing Department of Corrections' VirginiaCORIS system to   include the LIDS functionality. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund |  | $0 | 
   |  | $1,599,280 |  | 
   | Nongeneral Fund | $0 | $0 | 
 
 
| Agency Name / Project Title / Description | Start Date | Completion Date | Estimated Project Cost | 
   | Jamestown-Yorktown Foundation (425) -- Yorktown Museum   Replacement Technology | Dec 30, 2011 |  |  | 
   |  |  | Dec 31, 2016 | $2,395,000 | 
   | This project will install the requisite technology components   for the Yorktown Museum replacement project, including exhibit technology, audio   visual components, wireless, data and telecommunications.  The Yorktown   Museum Replacement project will improve the necessary IT infrastructure in   order to accommodate expected future visitation. |   |   |   | 
 
 
| Estimated Project Expenditures | FY 2013 | FY 2014 | 
   | General Fund | $0 | $0 | 
   | Nongeneral Fund |  |  | 
   |  | $146,000 | $747,000 | 
 
2. The Health Care Reform program office has been established by the Secretary of Health and Human Resources to address the American Recovery and Reinvestment Act (ARRA), the Patient Protection and Patient Affordability Act (PPACA), and the Medicaid Information Technology Architecture (MITA).  This program will be generating approximately 23 major as well as non-major projects and the total cost of the program over seven years is expected to be $93,043,146 with a cost to the Commonwealth of $9,773,220.  Projects will be established over the next four years.  The seven year costs include six years of operational expenses associated with the provider incentive program that sunsets in 2021.  New recurring Medicaid expenses are also reflected in the seven year cost estimates.  The projects and cost estimates in this paragraph include efforts to modernize eligibility determination systems within the Department of Social Services.