Item 400 | First Year - FY2005 | Second Year - FY2006 |
---|
|
|
Coastal Land Surveying and Mapping (51000) | $1,534,821 | $1,292,821 |
Wetlands and Bottomlands Management (51001) | FY2005 $1,169,556 | FY2006 $927,556 |
Coastal Land Surveying and Mapping (51002) | FY2005 $365,265 | FY2006 $365,265 |
Fund Sources: | | |
General | FY2005 $1,302,821 | FY2006 $1,060,821 |
Dedicated Special Revenue | FY2005 $50,000 | FY2006 $50,000 |
Federal Trust | FY2005 $182,000 | FY2006 $182,000 |
Authority: Title 28.2, Chapters 12, 13, 14, and 15; Title 62.1, Chapters 16 and 19, Code of Virginia.
Out of the amounts for Wetlands and Bottomlands Management is designated $250,000 in the first year and $8,000 in the second year for Virginia's share of an Army Corps of Engineers project to construct a seawall at Tangier Island. Any unexpended general fund balances designated for payment to the Army Corps of Engineers for the Tangier Island seawall project on June 30, 2005, and June 30, 2006, shall be reappropriated for expenditure for the same purpose.