Chief Patron: Subramanyam
SB 346: Solar Interconnection Regulation

Item 476 #3s

Item 476 #3s

First Year - FY2025 Second Year - FY2026
Independent Agencies
State Corporation Commission FY2025 $50,000 FY2026 $0 GF

Language
Page 526, line 20, strike "$35,827,443" and insert "$35,877,443".


Explanation

(This amendment provides $50,000 the first year for the potential impact of Senate Bill 346, which provides that an electric distribution company shall pay $1.00 per kilowatt per day for the costs of lost electricity production for any and all delays beyond the regulatory notice period required by State Corporation Commission related to net energy metering along with other regulation of solar interconnection and net metering.)