Item C-51 #1c

Item C-51 #1c

First Year - FY2025 Second Year - FY2026
Central Appropriations
Central Capital Outlay FY2025 $8,555,135 FY2026 $0 GF
FY2025 ($19,642,754) FY2026 $0 NGF

Language
Page 557, line 20, strike "$42,910,836" and insert "$31,823,217".

Page 557, line 25, strike "$42,910,836" and insert "$23,268,082".

Page 557, line 35, after "appropriated", insert:

"$8,555,135 the first year from the general fund".

Page 557, line 35, strike "$42,910,836" and insert "$23,268,082".

Page 557, after line 40, insert:

"423                   Department of Historic Resources   Construct Clermont Farm Barn Replacement (18642)".

Page 557, after line 45, insert:

"425                   Jamestown-Yorktown Foundation              Renovate the Susan Constant".

Page 558, after line 7, insert:

D.  The Director, Department of Planning and Budget, shall transfer to this item the remaining balance of Virginia Public Building Authority bond proceed authorization from project 995-18495, originally authorized in Item C-72 of Chapter 1289, 2020 Acts of Assembly and subsequently amended in Chapter 552, 2021 Acts of Assembly, Special Session I."



Explanation

(This amendment provides $8.6 million the first year from the general fund, and reduces nongeneral fund bond proceeds by $19.6 million, largely due to a redirection of excess bond proceeds from a previous project to this item. This amendment also modifies the list of qualified state agency projects for which construction authorization is provided.)