Menu
2011 Session

Budget Amendments - SB800 (Member Request)

View Budget Item
View Budget Item amendments

Chief Patron: Marsh
CCO: VCCS Preplanning

Item C-85 #2s

Item C-85 #2s

First Year - FY2011 Second Year - FY2012
Central Appropriations
Central Capital Outlay FY2011 $0 FY2012 $2,500,000 GF

Language
Page 445, line 47, strike "$1,132,050,000" and insert "$1,134,550,000".
Page 448, following line 32, insert:
"G. Included in this item is $2,500,000 from the general fund in the second year to complete preplanning studies on ten projects for the Virginia Community College System.  These projects shall be chosen to enhance education in science, technology, engineering, and mathematics (STEM); and promote affordable college access."


Explanation
(This amendment provides $2.5 million for preplanning of ten projects by the Virginia Community College System. )