Item C-25.10 | First Year - FY2023 | Second Year - FY2024 |
---|
|
|
Planning: Relocate Hampton Roads Agricultural Research and Extension Center (18652) | $500,000 | $0 |
Fund Sources: | | |
General | FY2023 $500,000 | FY2024 $0 |
Out of this appropriation, $500,000 the first year from the general fund is designated to begin planning the relocation of the Hampton Roads Agricultural Research and Extension Center. The Virginia Cooperative Extension and Agricultural Experiment Station shall report to the Chairs of the House Appropriations and Senate Finance and Appropriations Committees by December 15, 2022, on a plan to relocate the Hampton Roads Agricultural Research and Extension Center including timeline, suitable location requirements, and building and moving costs.