Menu
2011 Session

Budget Bill - HB1500 (Introduced)

Virginia Community College System

Item C-66

Item C-66

First Year - FY2011Second Year - FY2012
New Construction: Construct Historic Triangle Parking Lot, Phase II, Thomas Nelson (17623)$342,000$0
Fund Sources:  
Trust and AgencyFY2011 $342,000FY2012 $0

Additional funds provided in this Item are for cost overruns of a previously approved capital project authorized in 2008, (Chapter 879, 2008 Acts of Assembly).  The total cost of the project with the supplement is $6,000,000.