1. This Item authorizes the capital projects listed below to be financed pursuant to Article X, Section 9(d), Constitution of Virginia.
2. The appropriations for said capital projects are contained in the appropriation Items listed below and are subject to the conditions in § 2-0 F of this act.
3. The total amount listed in this Item includes $603,700,000 in bond proceeds.
Agency Name/ | | Project | Section |
Project Title | Item # | Code | 9(d) Bonds |
Christopher Newport University | | | |
Construct Ratcliffe Hall Addition | C-14 | 17567 | $8,350,000 |
Construct New Housing | C-14.10 | 17632 | $13,500,000 |
Land Acquisition | C-14.20 | 17633 | $20,000,000 |
Acquire Property | | | $82,000,000 |
Alumni House | C-14.40 | 17800 | $4,000,000 |
Special Collections Library Environmental Improvements | C-14.50 | 16774 | $3,035,000 |
College of William and Mary | | | |
Construct Integrated Science Center | C-15 | 16296 | $7,100,000 |
Improve Intercollegiate Athletic Facilities | C-16 | 17553 | $2,000,000 |
George Mason University | | | |
Renovate and Construct Physical Education Building Addition | C-24 | 17368 | $1,000,000 |
Construct Hotel Conference Center | C-25 | 17374 | $10,000,000 |
Construct Parking Deck IV | C-26 | 17569 | $27,233,000 |
Construct Southwest Campus Dining | C-28 | 17571 | $14,639,000 |
Construct Smithsonian Conservation and Research Center Housing and Dining | C-29 | 17572 | $2,338,000 |
Construct Parking Deck III, Phase II | C-30 | 17573 | $27,237,000 |
Construct West Campus Connector and Campus Entrances | C-31 | 17574 | $13,922,000 |
Construct East Campus Fields and Courts, Phase I | C-32 | 17575 | $3,249,000 |
Construct Track and Field Stadium | C-33 | 17576 | $8,320,000 |
Renovate West Fields | C-34 | 17577 | $3,194,000 |
Supplement Prince William Performing Arts | C-36.30 | 16745 | $5,000,000 |
Construct Swing Space and Data Center | C-36.50 | 17142 | $6,000,000 |
Construct Biocontainment Lab | C-36.20 | 17371 | $5,825,000 |
Student Union Building II Supplement | C-36.70 | 16253 | $8,000,000 |
James Madison University | | | |
Renovate and Expand Athletics and Recreation | C-38 | 17562 | $50,000,000 |
Acquire Rockingham Memorial Hall | C-39 | 17168 | $8,000,000 |
Acquire Grace Street Property | C-39.10 | 17793 | $6,000,000 |
University of Mary Washington | | | |
Construct Convocation Center | C-43 | 17021 | $2,000,000 |
Construct Residence Hall | C-44.40 | 17507 | $5,000,000 |
Norfolk State University | | | |
Renovate and expand Student Center Building | C-46.05 | 16873 | $7,500,000 |
Old Dominion University | | | |
Construct Powhatan Sports Complex | C-47 | 17483 | $11,707,000 |
Improve Webb University Center | C-50.20 | 17640 | $3,875,000 |
Radford University | | | |
Construct Parking Deck | C-51 | 17532 | $11,698,000 |
Construct Student Fitness Center | C-54 | 17563 | $32,000,000 |
Construct Addition to Hurlburt Hall | C-55 | 17564 | $10,000,000 |
University of Virginia | | | |
Construct Information Technology and Communications Data Center | C-61 | 17578 | $12,900,000 |
Virginia Commonwealth University | | | |
Construct Executive Conference Center, Monroe Park Campus Addition | C-65 | 17536 | $33,957,000 |
Construct West Grace Street Parking Deck | C-66 | 17566 | $24,250,000 |
Construct School of Medicine | C-67.05 | 17683 | $58,436,000 |
Renovate Massey Cancer Center Laboratory Support | C-67.10 | 17685 | $5,013,000 |
Virginia Community College System | | | |
Student Center, Portsmouth Campus | C-77 | 17397 | $4,306,000 |
Student Center, Chesapeake Campus | C-81.30 | 17625 | $20,753,000 |
Student Center, Virginia Beach Campus | C-81.40 | 17067 | $2,903,000 |
Student Center, Norfolk Campus | C-81.50 | 17068 | $1,663,000 |
Construct Student Recreation Center, Blue Ridge | C-81.56 | 17785 | $10,698,000 |
Construct Chesapeake Academic Building Site Infrastructure, Tidewater | C-81.58 | 17787 | $4,925,000 |
Virginia Military Institute | | | |
Construct South Hill Parking | C-84 | 17559 | $2,816,000 |
Construct Lackey Parking | C-85 | 17560 | $1,958,000 |
Virginia Polytechnic Institute and State University | | | |
Construct Basketball Practice Facility | C-86 | 17529 | $9,400,000 |
Construct McComas Hall Exterior Wall Structure | C-88 | 17556 | $6,000,000 |
Total for Nongeneral Fund Obligation Bonds 9(d) | | | $536,700,000 |