First Year - FY2007Second Year - FY2008
New Construction: Construct School of Engineering (16403)$3,032,000$2,224,000
Fund Sources:  
GeneralFY2007 $1,566,000FY2008 $2,224,000
Higher Education OperatingFY2007 $1,466,000FY2008 $0

This Item contains supplemental funding to construct the School of Engineering, Phase II originally authorized in 2002 (Chapter 814, 2002 Acts of Assembly).  Additional funds are also provided in this Item for equipment.  The total cost of the project with the supplement is $57,981,000.