Language Page 493, after line 14, insert:"C-48.10 New Construction: Construct Widewater State Park Phase II and Phase III $0 $29,600,000 Fund Sources: General $0 $29,600,000
Page 493, after line 14, insert:
"C-48.10 New Construction: Construct Widewater State Park Phase II and Phase III
$0
$29,600,000
Fund Sources: General
Explanation
(This amendment provides $29.6 million GF in the second year at the Department of Conservation and Recreation for the second and third phases of Widewater State Park's construction. Phase II ($8.3 million) funds the construction of roads, trails, picnic areas, parking, sewer, and stormwater. Phase III ($21.3 million) funds the construction of more roads, electricity, water treatment, campsites, cabins, bathhouses, and a canoe launch.)