1. This Item authorizes the capital projects listed below to be financed pursuant to Article X, Section 9(d), Constitution of Virginia.
2. The appropriations for said capital projects are contained in the appropriation Items listed below and are subject to the conditions in § 2-0 F of this act.
3. The total amount listed in this Item includes $136,787,000 $257,309,000 in bond proceeds.
Agency Name/ | Item # | Project | Section |
Project Title | | Code | 9(c d) Bonds |
College of William and Mary (204) | | | |
Improve Auxiliary Facilities | C-6 | 18112 | $10,000,000 |
Construct Wellness Center | C-6.50 | 18192 | $10,000,000 |
Virginia Polytechnic Institute and State University (208) | | | |
Replace Unified Communications System and Network | C-19.05 | 18183 | $8,803,000 |
Virginia Military Institute (211) | | | |
Renovate and Enlarge Stonewall Jackson House Museum Facilities | C-19.01 | 18175 | $1,392,000 |
Replace Crozet Hall Floor | C-19.02 | 18176 | $1,475,000 |
Improve Post Facilities, Phase III | C-19.03 | 18185 | $4,000,000 |
Longwood University (214) | | | |
Construct University Center | C-8.40 | 17893 | $11,012,000 |
University of Mary Washington (215) | | | |
Improve Battleground Athletic Complex Fields and Facilities | C-13.10 | 18133 | $10,142,000 |
Renovate Residence Halls | C-13.20 | 18177 | $15,175,000 |
James Madison University (216) | | | |
Construct Student Housing | C-8.35 | 18197 | $55,000,000 |
Radford University (217) | | | |
Renovate Athletics Complex | C-13 | 18120 | $8,000,000 |
Old Dominion University (221) | | | |
Replace the Webb University Center | C-12 | 17947 | $78,695,000 |
Virginia Commonwealth University (236) | | | |
Expand Main Street Parking Deck | C-16 | 18115 | $5,600,000 |
Upgrade Siegel Center | C-17 | 18116 | $12,000,000 |
Sanger Hall Phase II (Department of Pathology) | C-17.10 | 18070 | $7,500,000 |
Christopher Newport University (242) | | | |
Expand Athletic Facilities II | C-4.10 | 17361 | $4,730,000 |
George Mason University (247) | | | |
Construct Academic VII/Research III, Phase I | C-7.10 | 17999 | $8,935,000 |
Virginia Community College System (260) | | | |
Construct Parking Garage, Blue Ridge | C-18 | 18096 | $4,850,000 |
Total for Nongeneral Fund Obligation Bonds 9(d) | | | $136,787,000 |