Item C-290.20 (Not set out) | First Year - FY2007 | Second Year - FY2008 |
---|
|
|
New Construction: Replace St. Brides (15755) | $0 | $4,406,000 |
Fund Sources: | | |
General | FY2007 $0 | FY2008 $4,406,000 |
This Item contains supplemental funding for the second phase of the project to replace St. Brides Correctional Center, authorized in 2004 (Chapter 4, 2004 Special Session). Additional funds are also provided in this Item for equipment. The total cost of the second phase of the project with the supplement and equipment funding is $36,881,000.